Fighting for Commitment and Honor - A Record of the Construction Power Project of the Sanguan Crane Sword Orchid Expressway
Category:
Company News
Author:
Source:
Published Time:
2020-07-10
Plateau iron army competes for elegance, the former barren mountain has become a power station. Standing on the Lion Bridge hillside in Diannan Town, Jianchuan County, Dali Prefecture, what catches the eye is a silver sleeping lion shrouded in silver light. Its body is wide and flat, its color is silvery white and shiny, and its wings are rows of high and low voltage electrical equipment that shimmer with silver light and are neatly arranged; its brain is a 12500kVA transformer, emitting a low, guttural roar, like the snoring of a sleeping lion. This is the 35kV Lion Bridge substation, recently completed and successfully put into operation by the power supply project for the construction of the Sangu Department Hejianlan Expressway. Who would have thought that 40 days ago, this was still a wasteland!
Skilled and valiant troops Shouldering heavy responsibilities
The Hejianlan Expressway is a key construction project of Yunnan Province during the "13th Five-Year Plan" period, and it is also an 2020 important part of the province's county-level expressway network's "ability to connect and fully connect" in the year. The construction power supply project of the Hejianlan Expressway (Dali section) is approximately 80km long, starting from Heqing County, Dali Prefecture, passing through Eryuan County, and ending at Shaxi Ancient Town in Jianchuan County. The entire line includes 3 newly built 35kV substations, 2 newly added 35kV outgoing lines, newly built 35kV lines 4.2km and newly built 10kV lines 76km。
2019 year 8 month, the control project of the Hejianlan Expressway started. At the same time, the Sangu Department quickly dispatched personnel to form the Hejianlan Expressway construction power supply project and started construction. In the same year 9 month, the feasibility study report on the external power supply scheme for the construction power supply of the Hejianlan Expressway (Dali section) was officially approved by the Dali Prefecture Power Supply Bureau. The start of the control project of the expressway was imminent, and the construction of the power supply was urgent! However, due to the constraints of local land acquisition and demolition, sapling compensation, and natural weather, the initial progress of the project was not smooth, and even by 2020 year's Spring Festival holiday, the on-site construction progress was still lagging behind, and the situation was very severe.
But at this time, no one would have thought that 2020 year's Spring Festival, the real test had just begun, and an unavoidable pneumonia epidemic was coming.
Post-festival resumption of work The "anti-epidemic" war begins
2020 The spring of the year is destined to be unforgettable for everyone. At the beginning of the new year, a pneumonia epidemic caused by the novel coronavirus infection began to sweep across the country. No one would have thought that the Spring Festival holiday would be forced to extend from the original seven days. While the whole country was working together to fight the epidemic, the Sangu Department Hejianlan Expressway (Dali section) construction power supply project department actively responded to the requirements of the company and the command center for resuming work and production during the epidemic prevention and control period. Under the meticulous arrangement of the project department, all management personnel of the project department returned to their posts on 2 month 8 day. Under careful organization, by 2 month 20 day, the number of returned migrant workers reached 64 people. Under the premise of taking epidemic prevention and control measures, the project steadily promoted the resumption of work and production.
In order not to affect the overall progress plan of the Hejianlan Expressway, meet the power demand of the corresponding civil engineering construction area, and ensure the normal start of the control project. 2 month 21 day, Shi Xuhui, the company's assistant manager and manager of the Third Engineering Project Department, conducted a comprehensive investigation of the on-site work surface. In view of the scattered construction sites and long construction front, Shi Xuhui made reasonable adjustments to the on-site management personnel and transferred 7 management personnel from other projects to form a temporary assault team to rush to Jianchuan for support. At this point, the project management personnel and on-site construction personnel fully met the personnel configuration requirements for resuming work and production. The general contracting project management department specially rewarded the project department with 30 ten thousand yuan for its outstanding performance in resuming work and production during the epidemic prevention and control period.
2 month 25 day, the Hejianlan Expressway production promotion meeting clarified that the power construction energization time was 4 month 5 day, leaving the project department only 30 days for power construction! But under normal circumstances, it takes at least two months to build a new 35kV substation, from personnel entering the site to equipment installation, from equipment debugging to completion acceptance and power transmission by the power supply bureau.
The project management department was faced with the delay caused by the previous land acquisition impact. Currently, there are still 2 newly built substations, electrical installation parts, and 4.2km of 35kV lines and 26km of 10kV lines have not yet been constructed.
Is it possible to complete this arduous construction task within such a short period of time, under the enormous pressure of epidemic prevention and control work? — This is a question that lingers in the minds of every management personnel. However, honesty and trustworthiness are the principles that every "An'er person" has always upheld. Faced with the characteristics of tight deadlines, heavy tasks, and great difficulties in the construction power supply project of the Hejianlan Expressway (Dali section), the project department scientifically planned, reasonably arranged, continuously optimized the construction plan, increased manpower and machinery, and reversed the schedule to each day, strictly rewarding and punishing according to the node schedule. On the sand-filled hills and in the dense forests of the mountain streams, a wave of rapid work was quickly set off. At the same time, various departments of the project department continued to carry out self-inspection of quality and safety inspections, achieving quantitative assessment, high-quality quality, and controllable safety, ensuring that the on-site construction progress steadily advanced.
Broadening channels and meticulous and thorough supply guarantee. When the nationwide COVID-19 epidemic had not yet been completely controlled, very few enterprises in various industries were able to resume work smoothly. How to ensure the timely supply of various equipment and materials became a major problem. On the one hand, the project department actively sought help from the company and applied to the group company for issuing freight certificates for freight drivers. On the other hand, it urged equipment manufacturers to speed up production and arrange equipment transportation plans in advance. At the same time, relying on its own strength, it actively coordinated the purchase of commercial concrete locally. In the end, it ensured the 35kV orderly supply of materials for the foundation of large-scale equipment for newly built substations.
Refining responsibilities and quantitative assessment to promote progress. Given the tight construction schedule, heavy workload, and significant interference from overlapping construction, the project department actively communicated with the substation civil construction and electrical installation units. They prioritized electrical equipment installation, ensuring continuity and avoiding pollution and rework caused by overlapping construction. Responsibilities were also refined, clarifying the duties of management personnel and setting target milestones for each construction team. Daily and weekly assessments, with clear rewards and punishments promptly implemented, increased the work motivation of both the project management team and the construction teams.
Responsibility assigned to individuals; all staff participate in ensuring safety. To ensure safe production and achieve zero accidents, the project department signed safety responsibility agreements with each construction team's safety officer. They strictly enforced pre-shift safety education and inspection systems, deploying safety management personnel to the site for continuous monitoring, promptly identifying safety hazards, and ensuring comprehensive safety coverage.
Through a series of strong construction control measures, the Hekjianlan Expressway construction power supply project department, embodying the spirit of the plateau army—'able to endure hardship, fight bravely, and dedicate themselves, daring to fight tough battles, good at fighting tough battles, and capable of winning tough battles'—deeply implemented the Group's common behavioral principles of 'dedication, cherishing one's position, honesty and trustworthiness, and legal operation'. Within a short effective construction period of thirty days, they completed the construction of 35kV the Lion Bridge Substation, 35kV and the Hekjian Bridge Substation. These were 3 month 31 respectively 4 month 1 accepted by the Dali Prefecture Power Supply Bureau on 4 month 3 respectively 4 month 5 and the construction of the 35kV the Lion Bridge Substation, 35kV Hekjian Bridge Substation was successfully completed and energized on 4100 , with a total construction output value of approximately
yuan, successfully meeting the project's schedule and creating another miracle in the company's power construction history! 35kV the Lion Bridge Substation, 35kV With the successful commissioning and energization of the two new Hekjian Bridge substations, the Third Engineering Department's Hekjianlan Expressway construction power supply project department, after thirty days of intense work, submitted an excellent report to the company, general contractor, and owner! Now, with spring arriving and the epidemic receding, these builders, far from their families and the conveniences of city life, these tenacious and courageous fighters remain at their posts, using their diligence and wisdom to nurture the fruits of their labor and write even more magnificent chapters!
[Third Engineering Department / Chen Jinglei]