50-Day Rush: Company's Construction Projects Accelerate and Achieve Latest Progress ③


Category:

Company News

Author:

Source:

Published Time:

2023-12-20

The company, closely following the deployment requirements of the Group's "50-day intensive work plan to win the whole year" implementation plan, sounded the "assembly call" for the year-end battle, issuing a "mobilization order", calling on all cadres and employees to work with the spirit of a frontline charge, a courageous and forward-looking fighting posture, and an unyielding determination to seize production with full energy, strive for business operations, accelerate the construction progress of various ongoing projects, promote the company's high-quality development with high-quality project construction, and ensure the successful completion of all annual targets.

Luxi Water Plant Project of the Third Engineering Project Department Enters the "Fast Lane"

With the decrease in temperature and rainfall, the Luxi Water Plant project of the Third Engineering Project Department has officially entered the peak construction season. All employees of the project department are working hard, focusing on the production node of December 24th, continuously optimizing the construction plan, deploying scientifically, and making every effort to accelerate the project construction process.

While striving to achieve the node goals, the project department still firmly upholds the important concepts of "guaranteeing quality and safety" in the Group's "four guarantees, one tree, and one control", adhering to high standards and strict requirements, strengthening construction supervision, standardizing construction procedures, and ensuring that the project becomes a high-quality project that satisfies the owner and stands the test of time, striving to win the final battle of the year. To date, 80% of the building construction and water pool construction of the Luxi Water Plant project has been completed, 90% of the floating pump station assembly has been completed, and all water transmission pipelines have been laid.

Duobao Project of the Eighth Engineering Project Department: Laying a Solid "Foundation Stone"

At the end of the year, the Yunnan Duobao Cable Group Co., Ltd. Power New Materials Equipment Industrial Cluster Science and Technology Park project, as a key construction project of the company, has entered the crucial stage of the final sprint. Since the project was launched, the project management department has always adhered to the policy of "clarifying work priorities, strictly controlling on-site construction management, and accelerating the progress of project construction to achieve substantial progress", always upholding the philosophy of "emphasizing practical work, strong execution, and implementation", focusing on doing things, demonstrating abilities in doing things, working quickly and efficiently, and effectively improving work efficiency. Currently, the 1/13 axis D axis to G axis and 1/7 axis G axis to K axis of the three-story flower stand of the two factory buildings in the Power New Materials Equipment Industrial Cluster Science and Technology Park project have completed the pouring of the last batch of concrete, marking a step closer to the overall main body water cutoff for all building numbers, and laying the foundation for the overall main body water cutoff.

2023 The year is entering the "countdown". The project management department is using a visual management chart, and under the premise of ensuring quality and safety, is doing its utmost to accelerate the construction progress, calling on all staff to work hard, make a full sprint, and win the year. In the project, we continue to launch a tough offensive, making every effort to play a "combination punch" of element guarantees, pushing the project construction to run at an "accelerated speed", and comprehensively accelerating the sprint towards annual target tasks. [Eighth Engineering Project Department/Duan Yin]

Lincang Shuangjiang Project of the Ninth Engineering Project Department: Building a New "Cloud Ladder" for the People

The Shuangjiang Project Linmeng Line, undertaken by the Ninth Engineering Project Department, is the main street of Mengku Town. To ensure that the townspeople can enjoy their holidays with peace of mind, the project department and team members are working hard and have not relaxed for a moment, and are enthusiastically sprinting towards the node goals, even working overtime to complete the day's construction tasks.

Next, all cadres and employees of the project department will work together to strive to complete the renovation of the 1371m sidewalks on both sides of the Linmeng Line and the laying of power pipes and weak current pipes before the holiday. [Ninth Engineering Project Department/Li Xiubo]