Section 1 of the Tibet Giant Dragon Project successfully completed the pouring of 2300m³ of concrete for the No. 3 crushing station.
Category:
Company News
Homepage Recommended News
Author:
Source:
Published Time:
2024-04-07
Recently, the No. 1 section of the original ore system project of the Phase II expansion project of the Xizang Julong Copper Mine, after two days and two nights of intense work, successfully completed the remaining 2300m of the No. 3 raft slab at the north crushing station. ³ Concrete pouring work. Thus, No. 3 The foundation raft slab pouring work of the crushing station is completed.

The north crushing station construction area is located at an altitude of 5000 meters, with night temperatures as low as minus 8 degrees Celsius. To ensure the smooth pouring of this large-volume concrete, the project department planned in advance, deployed meticulously, formulated a detailed shift plan, reasonably arranged on-site personnel, actively coordinated with the owner, and formulated countermeasures in advance for potential problems during the pouring process. The cadres and employees of the project department worked together, making sufficient preparations in terms of concrete supply, safety measures, logistical support, and cold protection. Finally, after two days and two nights of hard work, the 2300m raft slab concrete pouring work of the No. 3 crushing station raft slab A-D axis intersection ①-⑩ axis was successfully completed. ³ The project department management team used practical actions to practice and carry forward the spirit of the plateau iron army and the old Tibet spirit, upholding the belief of "no lack of spirit despite lack of oxygen, not afraid of hardship, high altitude, higher realm," overcoming one difficulty after another. The successful pouring of the No. 3 crushing station raft slab concrete has been highly recognized by the owner, laying a solid foundation for completing subsequent construction node tasks. Next, the project management team will continue to enhance its sense of responsibility and mission, strictly follow the group's "four guarantees, one control, one tree" project management requirements, further strengthen project management level, improve engineering quality, and promote the company's high-quality development through practical actions. [Xizang Julong Project/Xu Zhaoxiong, Gao Yuanlong]
项目部管理团队用实际行动践行和发扬着高原铁军精神和老西藏精神,秉持“缺氧不缺精神、艰苦不怕吃苦、海拔高境界更高”的信念,攻克一个个难关。此次3#破碎站筏板混凝土的顺利浇筑得到了业主单位的高度认可,为完成后续施工节点任务奠定了坚实的基础。接下来,项目管理团队将不断增强责任感、使命感,严格按照集团“四保一控一树”项目管理要求,进一步强化项目管理水平,提升工程品质,笃行实干助推公司内涵式高质量发展。【西藏巨龙项目/徐照雄、高远龙】