The single-pile vertical static load test of the No. 2 Engineering Project Department's recycled copper resource recycling base construction project passed.


Category:

Company News

Author:

Source:

Published Time:

2024-06-18

6 On July 17, the No. 2 Engineering Project Department completed the single-pile vertical static load test for the Chuxiong Yunnan Nonferrous Metals Co., Ltd. recycled copper resource recycling base construction project - pyrometallurgical system engineering, 14 days ahead of schedule.

During the construction process, the project department actively overcame difficulties such as limited site conditions and rainy season construction, adopting measures such as "two shifts" to ensure the project progress and provide strong support for the early implementation of the single-pile vertical static load test. In the test, the detection ratio and pile number selection met the relevant standards and design drawings, the test data was true and effective, and all tests met the qualified standards.

The successful completion of this single-pile vertical static load test has laid a solid foundation for the smooth progress of the subsequent main project. [No. 2 Engineering Project Department/Yang Dongbin]