The 10kV switchgear and transformer in the high-voltage switch room of the Niu Matang project in Tibet, of the 13th Engineering Project Department, were successfully energized.
Category:
Company News
Author:
Source:
Published Time:
2024-07-08
7 On June 6th, the 10KV switchgear and transformer in the high-voltage switchgear room of the installation project for the Niu Matang heavy metal ion acidic water treatment project of Tibet Huatai Long, undertaken by the Thirteenth Engineering Project Department, were successfully energized.
This energization process was challenging and demanding. To ensure its success, the project department made advance plans and deployments, holding numerous safety briefings to meticulously review the operational procedures, clarifying safety key points and precautions for each step. Simultaneously, the power supply plan underwent repeated review and optimization to ensure its rationality and safety.
Before energization, the project department, strictly following the client's requirements, organized professional personnel to conduct comprehensive inspections and tests of the equipment, ensuring that all equipment met national safety standards. Furthermore, the project department diligently processed necessary procedures such as the power outage and energization operation permits, providing strong support for the smooth progress of the energization work.
During the energization process, the project department adopted a step-by-step approach, from the high-voltage input to the transformer and then to the low-voltage output, with each stage undergoing rigorous testing and inspection. Technical personnel monitored the equipment in real-time, ensuring the safety and accuracy of each energization stage. After several hours of intense work, the 10KV substation successfully achieved step-by-step external power supply, with all equipment operating normally, stable power indicators, and achieving the expected results.
Next, the project department will further improve the quality and efficiency of project construction, ensuring the timely completion of all tasks and laying a solid foundation for the smooth operation of the Niu Matang water treatment plant. [Thirteenth Engineering Project Department/Han Rui]