120-Day Battle | The Underground Integrated Pipe Gallery Project of Baoshan Central City by the Seven Ministries Passes Completion Acceptance
Category:
Company News
Author:
Source:
Published Time:
2021-01-08
On December 28, the Baoshan central urban area underground integrated pipe gallery project on Beiqi Road (Zhengyang North Road-Donghuan Road) and Lancheng Road (Beicheng Road-Bei eight Road), constructed by the Seventh Engineering Project Department, successfully passed the completion acceptance inspection.
The Baoshan central urban area Beiqi Road (Zhengyang North Road-Donghuan Road) integrated pipe gallery project (civil engineering included in the construction drawings) is approximately 6.794Km long and is the main east-west artery connecting the old city and the Qingyang group. The total length of the Lancheng Road (Beicheng Road to Bei eight Road) integrated pipe gallery project is 0.68Km. Beiqi Road (Zhengyang North Road-Donghuan Road) and Lancheng Road (Beicheng Road-Bei eight Road) are located in the northern part of Baoshan City's central urban area. This project includes the installation of multiple systems, including electrical, lighting, monitoring, ventilation, drainage, and fire protection.
This completion acceptance inspection checked and accepted the pipe gallery site, remote monitoring of the monitoring center, and completion documents, and conducted on-site special inspections of the functional trial operation of the project. After inspection and acceptance, the internal site of the pipe gallery was clean and orderly, the monitoring and detection system was stable, the fire linkage alarm trial operation was normal, the remote control feedback of the monitoring center was normal, and the document inspection was complete and orderly. The acceptance team unanimously agreed to rate the project construction quality as "excellent".
This Baoshan central urban area underground integrated pipe gallery project Beiqi Road (Zhengyang North Road-Donghuan Road) and Lancheng Road (Beicheng Road-Bei eight Road) The successful completion acceptance inspection paves the way for Seventh Engineering Project Department the subsequent acceptance of the Longquan section, and the project officially enters the stage of physical handover and operation of the pipe gallery.
[Seventh Engineering Department/Zhen Fangyun Editor/Du Ye]