Gu Yongmao went to Qujing Defang Nanotechnology Co., Ltd. to deploy the 15,000-ton annual output of lithium iron phosphate project.
Category:
Company News
Homepage Recommended News
Author:
Source:
Published Time:
2020-07-16
7 Month 10 Day, Gu Yongmao, the deputy secretary of the company's Party committee and chairman, went to Qujing Defang Nano Technology Co., Ltd.'s annual production 1.5 The project mobilization and deployment before the start of the 10,000-ton lithium iron phosphate project factory installation general contracting project. Xu Yanlu, chief engineer, and Guan Yanguang, assistant manager and manager of the Seventh Engineering Project Department, also went there.
Qujing Defang Nano Technology Co., Ltd. and Qujing Lintie Technology Co., Ltd. are both wholly-owned subsidiaries of Shenzhen Defang Nano Technology Co., Ltd., committed to the development and production of nano-material preparation technology , Applying nanotechnology to the preparation of lithium-ion battery materials, mainly used in new energy vehicles, energy storage, consumer electronics, etc., including applications in lithium-ion power battery industries such as BYD and CATL.
Because the construction drawings are not available, refer to similar completed projects Engineering quantity estimation of Qujing Lintie Technology Co., Ltd., Qujing Defang Nano Technology Project equipment installation total 300 sets, pipeline installation 12.5 ten thousand inches, total steel structure of brackets and platforms 150-200 tons, power cables 45000 meters, control cables 236000 meters, pressure transmitters, differential pressure transmitters, level gauges, flow meters, etc. 1000 points, anti-corrosion 12000 ㎡, insulation 6000 ㎡.
Because this project needs to be completed within 70 days, and it is the rainy season, the construction difficulty is high, and the peak construction period is expected to require 500 people. After inspecting the Qujing Defang Nano Technology project site, Gu Yongmao and his team finally decided that this project would be completed by the Third, Sixth, Seventh, and Twelfth Engineering Departments.
Gu Yongmao required that, firstly, after the project starts 35-40 days, the equipment installation must be completed, and the pipe rack platform installation must be completed 70% prefabricated pipeline installation 35% and the bridge frame and wiring pipe installation must be completed 30% . Secondly, all personnel of the project construction team composed of four engineering departments should fully understand the important strategic significance of completing this project for the company's future business development. Thirdly, fully carry forward the "two safety" spirit, work together, work hard, during the key period of project construction, reasonably organize and closely cooperate with the Defang Nano construction command, carefully construct, and under the premise of ensuring safety and quality, accelerate the coordination and cooperation of various links to ensure that within 70 days, the construction task will be successfully completed.
[Twelfth Engineering Department / Wang Lisheng]