The permanent power supply project of the Eleventh Ministry of Industry Yunnan JianTou Chuxiong Development Center was successfully energized and put into operation.
Category:
Company News
Author:
Source:
Published Time:
2020-05-26
5 Month 21 Day, the permanent power supply project of the Yunnan JianTou Chuxiong Development Center construction project undertaken by the Eleventh Construction Department successfully passed the acceptance inspection of the Power Supply Bureau and was energized and put into operation.
Before energization, after confirmation by the on-site construction personnel, the Chuxiong State Power Supply Bureau dispatching center began to issue energization instructions, and the main power supply was from 110kV Longtan substation to the newly built outgoing line interval power supply. In the evening 8 hour 30 minutes, the main power supply passed through the newly built 10kV Yihai North Bank special line into the Yihai North Bank switch station. In the evening 8 hour 50 minutes, a total of 3 impact closing tests were conducted on the main power supply equipment of the switch station. In the evening 9 hour 30 minutes, the backup power supply passed through the Yihai North Bank branch line T Yihai North Bank Line III from 10kV Dongjiao substation was introduced into the Yihai North Bank central switch station, and 3 impact closing tests were conducted on the backup power supply equipment. After the electrical phase matching work of the main and backup power supplies was completed, all equipment in the switch station operated normally.
The permanent power supply project of the Yunnan JianTou Chuxiong Development Center adopts dual power supply, setting up a central switch station and 6 distribution rooms. Since 2 Month 28 resumption of work and production, the project department has strictly followed the epidemic prevention and control requirements of the company and the owner. With the joint efforts of all project management personnel and construction teams, the project was successfully energized and put into operation, which was highly recognized by the owner.
[Eleventh Construction Department / Wan Zhenyu]