Yun Jing Lin Paper Co., Ltd.'s 60,000-ton daily paper project successfully receives its initial 10kV power supply.


Category:

Company News

Author:

Source:

Published Time:

2019-12-09

August 29 On the day, Yun Jing Lin Paper Co., Ltd.'s project, which was constructed by the company's 10th Construction Department, 6 10,000-ton daily living paper project 10 The 1000 kV system successfully received its first power supply, ensuring the construction party's node schedule and receiving their affirmation.

Due to the short construction period for electrical and instrumentation work, 60 kilometers of cables and thousands of cable heads needed to be completed within 3 months, along with the energization of more than 200 instruments, 18 high-voltage cabinets, 3 transformers, 4 high-voltage motors, nearly 100 high and low-voltage panels, and the energization and operation of more than 100 motors. This presented a significant challenge for the 10th Construction Department.

Especially during the installation of high-voltage cables, nearly 1000 meters of 3X185 square high-voltage cables were located mainly in the old factory area, with many twists and turns at a height of 7-8 meters, making construction difficult. Nearly 1000 meters of safety protection was required before laying. Coupled with the rainy season, working in the rain became the norm. Employee Chen Shunyong used his off-duty time to find cable spools at a nearby used car dismantling site. This type of high-pressure pipe was unavailable in Jinggu, so Kunming was immediately notified to send it down, ensuring the cable construction could proceed the next day.

To complete the node tasks, working late into the night became commonplace. During construction, it was discovered that the interlocking cables affecting high-voltage power transmission were incorrect. Employees Zhang Haitao, Zhao Yonghua, and others worked overtime with their team until one or two o'clock in the morning until the problem was resolved. Issues raised that day were rectified and completed on the same day, ensuring power transmission.

Ensuring the node requires control at every stage and the dedication of every individual. Overcoming the disadvantages of insufficient construction technicians, short timeframes, and a lack of skilled workers, we worked hard and never gave up in the face of difficulties. This is also the essence of the "Second Safety" spirit.

 

  10th Construction Department/Zhao Junbo