The 10kV power supply and distribution project substation for the Wuhua District People's Hospital and Wuhua District Health and Wellness Center project has successfully passed acceptance and been successfully energized and put into operation.


Category:

Company News

Author:

Source:

Published Time:

2025-05-13

On May 11, the 10kV power supply and distribution project of Wuhua District People's Hospital and Wuhua District Health Care Center, constructed by the Eleventh Engineering Project Department of the company, successfully passed the acceptance inspection of the Wuhua District Power Supply Bureau and was successfully energized and put into operation. This achievement was completed 7 days ahead of schedule, accelerating the project construction.

This project consists of two substations and two diesel generator rooms, involving the installation and commissioning of 2 sets of outdoor ring network cabinets, 10 transformers, 26 high-voltage cabinets, and 105 low-voltage cabinets.

To ensure the smooth progress of the energization work, the project department planned and deployed in advance, carefully combed through the operation process, and clarified the safety points and precautions for each link. Before energization, the project department strictly followed the normative requirements, organized professional personnel to conduct comprehensive inspections and tests of the equipment, ensuring that all equipment met national safety standards, providing a strong guarantee for the smooth progress of the energization work.

During the energization process, the project department adopted a step-by-step approach, from outdoor ring network cabinets to high-voltage cabinets, and then to transformers. Technical personnel monitored the equipment in real time to ensure that each level of energization was safe and error-free. Finally, the high-voltage cabinets, transformers, and low-voltage distribution cabinets in the two substations were successfully energized and put into operation, with all equipment operating normally and stable power indicators.

The successful acceptance, energization, and commissioning of the substation not only provides stable and reliable power support for the hospital but also lays a solid foundation for the subsequent commissioning of various professional equipment, fire protection, and completion acceptance. [Eleventh Engineering Project Department/Li Yipeng]