100-Day Intensive Effort | Company Cloud Copper Relocation Project's Integrated Corridor Completed


Category:

Company News

Author:

Source:

Published Time:

2024-09-25

9 On August 24th, with the successful hoisting and installation of the ninth steel truss on the north line, the comprehensive corridor of the public works project for the relocation project of Yunnan Copper Industry Co., Ltd., Southwest Copper Branch of the company, was officially completed.

The steel structure of the project's comprehensive corridor weighs nearly 6000 tons, with a total straight-line distance of 6000 meters, making it one of the main parts of the project construction. During the construction process, faced with difficulties such as limited factory area roads, the project department actively responded and carefully planned, overcoming difficulties through measures such as optimizing the construction plan and strengthening on-site coordination, ensuring the smooth transportation and hoisting of the trusses. Finally, through the joint efforts of all cadres and employees of the project department, all nine trusses were successfully hoisted, marking a successful completion of the comprehensive corridor construction task.

Next, the project department will continue to overcome difficulties, further strengthen the project quality, progress, and safety management work, and make every effort to promote the subsequent construction tasks such as pipeline installation and cable laying. [Sixth Engineering Project Department/Chu Wenlin]