The company, closely following the deployment requirements of the Group's "50-day intensive work plan to win the whole year" implementation plan, sounded the "assembly call" for the year-end battle, issuing a "mobilization order", calling on all cadres and employees to work with the spirit of a frontline charge, a courageous and forward-looking fighting posture, and an unyielding determination to seize production with full energy, strive for business operations, accelerate the construction progress of various ongoing projects, promote the company's high-quality development with high-quality project construction, and ensure the successful completion of all annual targets.

The Third Engineering Project Department's Guning Expressway Project: Full Speed Ahead

Winter has arrived, and the temperature difference between day and night is large in Lijiang, with the lowest temperature reaching below zero. Despite the cold wind, the project management personnel and team members of the Guning Expressway power supply project are working day and night to install power lines and transformers to ensure the smooth and orderly progress of the project, paving the way for the Guning Expressway to achieve its opening goal. Under the careful planning and reasonable arrangement of the project department, the Guning Expressway power supply project's city ring section has been completed and is moving towards the next milestone.

The Eighth Engineering Project Department's Yiliang Project: Building a Solid Foundation

As winter approaches and temperatures plummet, the construction site is bustling with activity. Vehicles shuttle back and forth, the sounds of breaking bricks and stones, the hammering of electric drills, and the shouts of workers blend together, creating a lively scene. The Eighth Engineering Project Department's Yiliang County Rural Human Settlement Environment Improvement Construction PPP project is fully underway, encompassing the renovation of sewage pipe networks and the construction of sewage treatment plants in six townships. Faced with tight deadlines, heavy tasks, and complex and changeable construction conditions in the townships, all personnel in the project department are working diligently in their respective positions to ensure the completion of tasks with high quality and quantity.

Currently, a total of 24,000 meters of new township sewage pipe networks have been completed in various townships (80% of the total construction progress); the construction of the main buildings, structures, and equipment of four township sewage treatment plants has been basically completed, and one sewage treatment plant has been completed and put into operation (65% of the total construction progress). All construction work is proceeding in an orderly manner. The project department will surely complete the renovation of all township sewage pipe networks and the construction of sewage treatment plants by April 30, 2024, contributing to the improvement of the human settlement environment in Yiliang County, the construction of beautiful and livable villages, and the realization of rural revitalization. [Eighth Engineering Project Department/Liu Jiachang]

Xinping Photovoltaic Power Generation Substation Project of the Industrial Workers Center: Finding the Greatest Common Divisor

Winter has arrived, and we are now in the crucial final sprint stage of the year-end. All employees of the electrical equipment installation team dispatched by the Industrial Workers Center are working hard on the front line of the project, promoting the project progress with practical actions and striving to complete the power transmission task on schedule.

While accelerating the project progress, the team strictly implements the management requirements of the company and the project department, giving full play to the spirit of the industrial workers' center of not being afraid of hardship or fatigue, and adhering to hard work. They firmly uphold the bottom line of construction safety and installation quality, adhere to a problem-solving approach, carefully analyze current construction difficulties, overcome challenges one by one, and reasonably arrange construction plans based on the existing work surface. Currently, various project completion work is proceeding in an orderly manner as planned. [Industrial Workers Center/Zhang Zheng]