50-Day Rush | The 13th Engineering Project Department completes the large-scale equipment hoisting node task ahead of schedule for the Xizang Niumatang project


Category:

Company News

Homepage Recommended News

Author:

Source:

Published Time:

2023-12-20

Recently, under the joint supervision of the project management department of the construction unit, the safety production department, and the person in charge of the supervision unit, the large-scale equipment installation node task of the Niumatang heavy metal ion acidic water treatment project of the Thirteenth Engineering Department was completed ahead of schedule.

The project is located in Jiuma Township, Mozhugongka County, Lhasa City, Tibet Autonomous Region, with an altitude of 4550 meters and a temperature as low as -10℃. Since the commencement of the project, the project department has strictly followed the group's "four guarantees, one control, and one tree planting" project management requirements, implemented various safety production measures in detail, strengthened the control of the entire construction process, and with a sense of urgency of "the opening is the decisive battle, and the starting point is to accelerate", systematically planned the project management work, and further clarified the target tasks. During the project construction process, all personnel of the project department firmly established a sense of service and responsibility, ultimately ensuring the successful completion of the task. [Thirteenth Engineering Project Department/Han Rui]