On December 30th, a simple yet grand topping-off ceremony was held at the construction site for the 47,000-ton/year environmentally friendly adhesive (including adhesive powder) technical transformation project's steel structure and equipment installation project of Yunnan Zhengbang Technology Co., Ltd., undertaken by the Sixth Engineering Project Department.

At the ceremony, the project manager, representing the contractor, stated: During the construction process, the project site earnestly implemented the Group's "Four Guarantees, One Control, and One Cultivation" implementation details, pursuing excellence and striving for perfection. Through scientific management and meticulous construction, the steel structure main body of the Zhengbang technical transformation project was completed on schedule and with high quality.
With the command "Begin topping-off," a 50-ton truck crane slowly installed the last floor steel plate. Witnessed by all personnel, the main structure topping-off of the Zhengbang technical transformation project was successfully completed. The project department will continue to strive with full enthusiasm and confidence to complete the Zhengbang technical transformation project.
[Sixth Engineering Department Text/Sun Jian Photo/Liang Qing Editor/Hu Hengjin]