The Dali Three Reservoirs Interconnection Phase II project successfully achieved its construction schedule target.
Category:
Company News
Author:
Source:
Published Time:
2018-06-29
On June 25th, with the completion of the welding of the last weld on the 3# outlet (the interface between the second and first phases), the pipeline installation project of the Dali Three Reservoirs Connection Phase II Project, Area 4, undertaken by the Sixth Construction Department, was successfully completed and is ready for water delivery. It also won first place again in the general contractor's assessment of safety, quality, and progress across seven work areas.
The pipeline installation project in Area 4, officially started on April 20th and completed on June 25th, lasted 65 days. Although the project started 20 days later than other projects, it was completed 5 days ahead of schedule. The project department received multiple commendations and awards in the general contractor's weekly safety, quality, and progress assessments, receiving a total of 110,000 yuan in bonuses, the highest among the seven work areas. During the project implementation, the project department's safety management, quality control, and technical visa completion and approval work also received multiple commendations from the general contractor and the supervisor.
The successful implementation and efficient advancement of the Three Reservoirs Connection Phase II Project have received high praise and appreciation from the owner, general contractor, and supervisor, fully demonstrating the Sixth Construction Department's excellent control capabilities, good communication and coordination capabilities, and professional and efficient construction capabilities in this project.

[Sixth Construction Department, Chu Wenlin]