The turbine cover of the Qi Gongbu Vietnam Spring Project Department was successfully installed.
Category:
Company News
Author:
Source:
Published Time:
2018-06-21
The 24.8MW waste heat power generation project turbine installation work for the Vietnam Xuancheng 2500t/d+12500t/d clinker production line, after 77 days of hard work, was successfully capped after 14 continuous hours of work, witnessed by the owner: XUAN THANH CEMENT J.S.C., supervisor: CONINCO, Anhui Conch Kawasaki Engineering Co., Ltd., and China Energy Construction Group Hunan Thermal Power Construction Co., Ltd. This is a major milestone in the project and has been highly praised by all parties.

Figure 1: General Assembly Process

Figure 2: Successful Capping
[Seven Construction Department Qiu Dong]