50-Day Rush: Company's Construction Projects Accelerate and Achieve Latest Progress⑥
Category:
Company News
Author:
Source:
Published Time:
2023-12-26
The company, closely following the deployment requirements of the Group's "50-day intensive work plan to win the year" implementation plan, sounded the "assembly call" for the year-end battle, issuing a "mobilization order", calling on all cadres and employees to work with the spirit of a frontline charge, a courageous and forward-looking fighting posture, and an unyielding determination to seize production with full energy, strive for business operations with all their might, accelerate the construction progress of various ongoing projects, promote the company's high-quality development with high-quality project construction, and ensure the successful completion of all annual targets.
The Third Engineering Project Department's Miyu Expressway Project Achieves Construction Acceleration
On a cold winter night, the construction site of the Wushan toll station on the Miyu Expressway project is bustling with activity. Under the meticulous organization of the project department's construction management personnel, various construction tasks are proceeding in an orderly manner.

To complete the target tasks set by the general contractor, all participants in the Miyu Expressway project overcame difficulties, stayed at their posts, and raced against time. To date, the renovation of the Wushan toll station's toll canopy has been successfully completed, laying a solid foundation for achieving the annual target tasks.
The Seventh Engineering Project Department's Vietnam He Fa Project Launches a General Mobilization for the Final Push
Currently, Vietnam is in the rainy season, which has created some obstacles to project construction. To better carry out the "50-day intensive work" project construction, the project department actively overcomes difficulties and mobilizes all cadres and employees to strive for the full completion of annual targets.

During the project construction process, the project department management personnel continuously strengthened the control of technology, safety, and quality, planning ahead to ensure the supply of materials and mechanical equipment. At the same time, the project department improved the leadership cadre duty system and logistics support service mechanism, providing strong support for project construction. To date, the Vietnam He Fa project has completed the installation of the baghouse dust collector body, ash silo body, and part of the absorption tower inlet flue, and subsequent construction is proceeding rapidly. [Seventh Engineering Project Department/Li Li]
The Thirteenth Engineering Project Department's Tibet Julong Project Area 2 Launches an All-Out Decisive Battle
The Tibet Julong Copper Mine Phase II Expansion Project's original ore system project Area 2 is located at the North Crusher Station at an altitude of 5100 meters. During the construction process, project members overcame physical discomfort caused by high altitude and hypoxia, and steadily advanced the project construction according to the construction plan. Currently, the No. 3 crusher station has completed the earthwork excavation and pile head demolition tasks and has entered the raft foundation reinforcement binding stage (total 700 tons, 50% completed).

The project department takes a firm grip on engineering nodes as an important measure, reasonably arranges weekly construction plans, strengthens the implementation of daily production tasks, insists on on-site command by cadres, on-site understanding of the situation, and on-site problem-solving, and has held several construction progress promotion meetings, leading all project personnel to devote themselves wholeheartedly to project construction, further creating a wave of rapid construction, and promoting early results and tangible results. [Thirteenth Engineering Project Department/Li Shiying]