100-Day Intensive Campaign | Successful Energization of the 10kV High and Low Voltage Power Distribution System in the Boiler Room of Company Tibet Giant Dragon Project #1


Category:

Company News

Author:

Source:

Published Time:

2024-11-18

Recently, through the tireless efforts and hard work of all members of the Tibet Giant Dragon Phase II project, the 1# boiler room 10kV high and low voltage power distribution system was successfully installed and energized.

During the project's progress, faced with complex line laying, tight time constraints, and the oxygen-deficient environment and biting wind and snow at an altitude of 5200m, the project team members did not flinch. They worked overtime to seize the construction schedule. In addition, to ensure the smooth progress of the electrical installation work, the company's safety director went to the project site every day with the construction workers to supervise and guide the electrical installation process and safety precautions.

Finally, after overcoming a series of technical difficulties and the impact of bad weather, the 1# boiler room 10kV high and low voltage power distribution system was successfully energized, completing the first node target task of electrical installation in this project and laying a solid foundation for subsequent installation work. [Tibet Giant Dragon Project/Pu Tongtao, Duan Kai]