The power supply for the Cloud Big Hospital power distribution system renovation project of the Third Engineering Project Department has been successfully delivered.
Category:
Company News
Author:
Source:
Published Time:
2024-06-16
6 On December 12, the power supply transformation project for Buildings 1 and 2 of the First Affiliated Hospital of Kunming Medical University, undertaken by the Third Engineering Project Department, was successfully energized for the first time, receiving high recognition from the owner, supervisor, and the Wuhu District Power Supply Bureau.

During the project construction process, the project department overcame difficulties such as a large and complex load and a lack of original switchroom drawings. They conducted a thorough investigation of the on-site power usage and, based on the project's actual situation, developed a targeted power relocation plan. Simultaneously, the project department further clarified key procedures and job responsibilities, ensuring seamless connection at each stage and providing a solid guarantee for the project's successful energization.
This successful energization marks a significant milestone for the project. In the following construction, the project department employees will continue to dedicate themselves to their work with superb skills, excellent work style, and a spirit of responsibility, steadily advancing to contribute more to the development of the company and the department. [Third Engineering Project Department/Deng Qinyuan]