The Nan Yun Lindian project of the Third Engineering Project Department successfully completed the hoisting task of the 12500KVA main transformer at the 35kv temporary substation.
Category:
Company News
Author:
Source:
Published Time:
2024-04-18
4 On May 16, the 35kv temporary substation 12500KVA main transformer hoisting task of the Nanyun temporary power supply project, undertaken by the Third Engineering Project Department, was successfully completed, laying a solid foundation for achieving the project's May 15 power-on target.

Before the hoisting operation, the project department management personnel went to the site early to conduct a site survey, plan the hoisting operation process, and confirm the safety conditions before hoisting. During the hoisting process, the project department actively overcame unfavorable factors such as limited construction site and complex external environment, and strictly followed the construction plan to hoist the main transformer to the main transformer foundation, finally successfully completing the hoisting task.
Next, the project department will continue to focus on the May 15 power-on target, coordinating overall planning, paying attention to details, careful planning, earnestly implementing the company's various management requirements, effectively strengthening progress control, comprehensively improving project management capabilities, and ensuring timely and efficient fulfillment of the contract. [Third Engineering Project Department/Liu Zhongyun]
previous page: