The 29MW generator of the Qi Gongbu Vietnam Zhenglong Pingyang Thermal Power Plant successfully grid-connected for the first time.


Category:

Company News

Author:

Source:

Published Time:

2018-08-29

8 Month 25 Day The thermal power plant project of Vietnam's Zhenglong Binh Duong Manufacturing Co., Ltd., constructed by Qigong Department, successfully achieved its first power grid connection after phase sequence approval and a series of tests and inspections.

This project was designed and general contracted by China Light Industry Changsha Design Institute, with Qigong Department as the installation and commissioning unit. The steam turbine was manufactured by Siemens (Czech Republic), and the generator was manufactured by ABB Company, with a capacity of 29MW 。After successful grid connection, operational performance testing will be carried out according to relevant standards, and after completion of the operational performance testing, it will be handed over to the user unit.

The successful completion of the project has accumulated certain experience for Qigong Department in the organization and implementation of industrial projects such as thermal power generation, and projects in Vietnam and overseas.

 Yunnan Construction Investment No.2 Installation Engineering Company  

 Yunnan Construction Investment No.2 Installation Engineering Company  

 Yunnan Construction Investment No.2 Installation Engineering Company  

[Qigong Department Liu Quan]

< 1...345...214 > 跳转到