Company's Tibet Julong Project Section 1 completes the construction task of the No. 4 crusher station retaining wall ahead of schedule


Category:

Company News

Author:

Source:

Published Time:

2024-08-26

Recently, the No. 4 crusher station of the Phase II expansion project of the Tibet Julong Copper Mine's original ore system project, Package 1, completed the construction of the 8.30 retaining wall ahead of schedule.

4# The foundation raft slabs of the No. 4 crusher station (D-G axis intersecting ①-⑩ axis; A-D axis intersecting ①-⑩ axis) were completed in late April and late May this year, respectively. After that, the main body construction of the retaining wall began, with a total concrete pouring volume of 7648 cubic meters. During the project construction, the project department carefully organized and scientifically planned the work, allocating over 60 workers and one tower crane and one crane according to the schedule. Finally, under the reasonable overall planning of the project department and the unremitting efforts of the on-site management personnel, the construction of the No. 4 crusher station retaining wall was successfully completed, one week ahead of schedule.

The completion of the No. 4 station retaining wall is another key breakthrough following the completion of the 6.30 node task of the No. 3 crusher station, marking the completion of the most challenging construction task of the north crusher station. Next, the construction of the remaining corridors and the electrical room of the north crusher station will be carried out. The project department will continue to uphold and carry forward the spirit of overcoming difficulties and strive to promote project construction. [Tibet Julong Project/Gao Yuanlong]