The 9# gallery ±0 meter pouring work of the first section of the Tibet Julong project of the company has been successfully completed.
Category:
Company News
Author:
Source:
Published Time:
2024-08-17
8 On August 15th, the No. 9 ore passageway (20-21/D-K axis (-4.80m~±0.00m)) column, side wall, beam, and slab pouring work for the first section of the original ore system project of the second phase expansion and renovation project of the Tibet Julong Copper Mine was successfully completed.
This pouring work began at 1 p.m. on August 14th and was completed at 4 a.m. on the 15th after more than ten hours of intensive construction. To ensure the smooth progress of the pouring work, before the operation, the project department management personnel communicated with the mixing plant to ensure the continuous supply of concrete while ensuring quality. During the pouring process, the project department strictly implemented construction specifications and quality standards, conducted strict inspection and testing of incoming materials, and actively contacted the construction unit and the supervision unit to jointly control and inspect the entire pouring process.
The successful completion of the ±0m pouring work of the No. 9 passageway not only provides valuable experience and a mature construction plan for the subsequent pouring work of the No. 7, 10, and 11 passageways at -4.8m and ±0.00m, but also provides a reliable guarantee for the efficient construction of the next phase of the original ore system. [Tibet Julong Project/Gao Yuanlong]
previous page: