The reactor offloading task at the Wugongbu Laos refinery project was completed safely.


Category:

Company News

Author:

Source:

Published Time:

2019-12-09

10 Month 7 Day Lao Zhongdong Petrochemical Co., Ltd. refined oil project 50 10,000-ton diesel hydrotreater and sulfur recovery hydrotreater ( 237 ton) safe unloading.

10 Month 5 Day The lower section of the hydrorefining reactor (gross weight 107.5 tons) unloading work began. To ensure safety, based on the actual on-site conditions, a gantry crane was used for unloading. Before unloading, the relevant plan had been submitted to the company for review, and the owner, supervisor, and general contractor had also approved it. Unloading was uniformly commanded by the company's hoisting master, Liu Sijie. At 0:30 on October 6 4 the lower section of the reactor landed safely on the support. Using the same method, on the afternoon of October 7 19 the upper section of the reactor (gross weight 129 tons) also landed safely. During the unloading process, the on-site leaders of the general contractor's Group International Department also repeatedly supervised safety and progress.

With the efforts of the project department employees, the unloading of the heaviest equipment for the Laos refinery project was successfully completed, accumulating experience for the subsequent reactor hoisting.

 

 

Fifth Department/Xu Kui Ping